Zesco injects $2.3m in Ndola substations

CHIMWEMWE MWALE, Ndola
ZESCO Limited has spent US$2.3 million to refurbish the 11 kilovolt switch gears at substations in Ndola to improve supply in the central business district.
The substations are Depot road, Itawa Water Works and Boart Longyear.
The 12-month projects, which started in August 2019, were scheduled for completion in August this year, but were delayed by effects of the coronavirus pandemic.
The projects, which are at about 65 percent completion level, are expected to be completed by December this year.
Zesco Ndola regional manager Yobo Mukonka said the refurbishment of the substations is aimed at increasing the security of supply in the CLICK TO READ MORE